NIOA Brisbane Office Featured in "Timber & Forestry E-News"

Timber & Forestry eNews - ' Mass-ive Project sets new pace for engineered wood "
Timber & Forestry eNews - ' Mass-ive Project sets new pace for engineered wood " - 2 page Article Spread

Our design for the Brisbane located, NIOA Timber Tower at the Brisbane Airport has been featured in Timber & Forestry E-news for setting new pace for engineered timber.

Read More

Full Article
Mass-ive project sets new pace for engineered wood - Timber & Forestry E-News - Publication Issue 645 - February 2021

Project Page
NIOA Brisbane Office Expansion

Using all prefabricated engineered timber for the structure means we have minimal waste on site, less trades on site, faster, quieter construction and a far cleaner site than what we see with a traditional construction project.

Ben Rowlands
Site Manager

We forecast the structure to take 36 days for completion, but we are on track to be complete in just 26 days in total. Part of the construction brief from the client was to ensure we do not hinder the day-to-day operations of the busy NIOA facility so the quicker we can construct and cleaner we can keep the site, the better.

Ben Rowlands
Site Manager

The building was a new typology, column-free space to enhance the experience for those working within it.

Dr. Andrew Magub
Principal Architect - KIRK